UC Davis Health / Jackson Construction
Private
Sacramento
$9,381,531
July 2021-December 2023
Commercial-Industrial & Distribution
This build-to-suit leased project involves the construction of an approximately 92,000 SF mixed-use pharmacy fulfillment center under a design-build platform between Jackson Construction and the University of California Davis Health. This state-of-the-art facility is outfitted with advanced medication inventory and distribution equipment designed to ensure the optimization of pharmaceuticals for inpatient and outpatient care. These include a conveyor belt system, negative air pressure clean rooms, a kidney dialysis center, offices, and storage areas. Royal Electric’s scope included site work as well as the installation of the building’s power system, specialty lighting, and low voltage systems.
Lease negotiation delays caused the project to incur timeline challanges.
In order to help the client get the schedule on track following lease negotiation delays, our team developed prefabricated 20’ sectional duct banks for all underground systems and 10’ sectional overhead conduit, reducing scheduled site durations and accelerating the pace of installations.