This project involved the demolition of existing structures along with the construction of 38,ooo square foot building; which included classrooms, administrative spaces and a 3,400 square foot common area.

Royal Electric oversaw and installed all electrical components including new 12kv service to feed the building 1200amp service at 277v/480v, in addition to all services from the 12kv to the 120v receptacles.

We also supervised the subcontracting of fire alarm, audio visual, telecommunications and security components of the project. The project was performed to LEED Gold status. Building Information Modeling (BIM) was utilized to coordinate work with the MEP.

 

project details
Owner :
University of California, Davis
General Contractor :
Flint Builders
Contract Value :
$3,078,985
Contract Time :
September 2014 – May 2016